During August, two separate power failures knocked out two separate railway control centres and brought significant parts of the UK rail network to a standstill. The first, a 90-second mains outage in Manchester on 6 August, took out Network Rail’s Rail Operating Centre and cascaded across six train operators. It’s been reported that the backup generator failed to start immediately, signals defaulted to red, and the resulting disruption ran well into the following day.
The second incident, on 22 August, hit CrossCountry’s only working control room at its Birmingham headquarters. A localised power cut affecting fewer than 90 customers in the area left the operator without power for almost 36 hours, with nearly an entire day’s services cancelled. Reports suggest there was no ready backup location and no working standby power on site.
Two incidents, two different operators, but the same underlying question: when the mains failed, why didn’t the backup do its job?
I’ve spent more than 25 years in the power generation sector, much of it working on critical infrastructure projects, including rail. While I don’t know the specifics of either site, the pattern these incidents reveal is one I’ve seen repeatedly, and it comes down to a set of decisions that are often made badly, or not made at all.
The seconds that matter most
A standby generator isn’t running continuously. When the mains drops, there is always a short break while the set starts, comes up to speed and takes the load. That happens within seconds, but it isn’t instantaneous.
For many applications, a few seconds of latent supply doesn’t matter. But for safety-critical signalling, it can be the difference between riding out a disturbance and triggering a full shutdown. When a signalling system loses certainty about where trains are, the correct response is to stop everything. That’s the system doing exactly what it should. But it means the resilience of the power supply behind signalling carries an importance it wouldn’t in most other settings.
This is where specification decisions made at the design stage become critical. For any load where even a few seconds of interruption is unacceptable, an uninterruptible power supply (UPS) should sit between the mains and the equipment. A UPS is essentially a fast-acting battery system that holds the critical load the instant the mains drops, bridging the gap while the generator starts and takes over. Data centres invest heavily in this protection because they operate to a zero-downtime standard. Safety-critical railway signalling belongs in exactly the same category of thinking.
Equally important is what happens once the generator is running. A set can be up to speed and ready to deliver power, but if the automatic transfer switch fails to complete the changeover from mains to generator, the site stays dark. The transfer switch monitors the incoming supply, signals the generator to start, breaks the connection to the failed mains and makes the connection to the generator. If this mechanism fails, through a fault or because it has never been properly tested under real conditions, the generator runs without supplying anything. From the outside it looks like the generator has failed, but in reality, the breakdown is a failed transfer.
These are perhaps two of the most common reasons backup systems fail to perform when called on.
The infrastructure behind the infrastructure
A generator is only ever as reliable as the infrastructure around it. The cables, connections, fuel system, tank integrity, starter batteries, coolant and control systems all need to be maintained, monitored and protected. However capable a generating set, neglecting any part of this chain introduces risk.
Fuel is a good example. Diesel that has been sitting in a tank for months can degrade, particularly if water ingress has occurred. Starter batteries lose charge over time, and control systems can develop faults that only show up when the set is asked to run under genuine load. None of these are dramatic failures; they’re the slow erosion of plant readiness that only becomes visible when the set is required to perform.
The CrossCountry incident raises a more fundamental point. If reports are accurate that there was no working standby power at the operator’s only control room, the issue isn’t a failed generator. It’s the absence of one.
What makes the CrossCountry case particularly instructive is the reported detail. The wider area lost power for a matter of hours, with most customers restored the same evening. But a fault within the building itself meant the operator’s headquarters stayed dark for almost 36 hours. The vulnerability wasn’t just the grid but inside the building; a reminder that internal electrical infrastructure needs the same level of scrutiny as the external supply that feeds it.
Testing: where most organisations fall short
Specification tends to get proper attention at the design stage. This means the generator rating, the coverage, and the criticality of the transfer time. These are usually addressed carefully up front. The problems tend to arrive later, once a set is commissioned, particularly if the maintenance routine starts to slip.
A weekly visual start-up, checking for leaks and obstructions, is valuable. But far fewer organisations run the test that actually proves readiness: a monthly transfer of the full site load to the generator, simulating a genuine mains failure. Fewer still carry out a longer annual full-load test to confirm the set still meets its rated output.
This distinction is vital, because a diesel engine that only ever runs off-load or lightly loaded can begin to wet-stack. This is where unburnt fuel collects in the exhaust system and, over time, undermines reliability. A generator that starts cleanly on a visual check could still fail under real load. The only way to prove it works is to make it work.
Remote monitoring does help catch developing faults between service visits, but it doesn’t replace investigative, on-site maintenance. A set that looks healthy on a dashboard can still need hands-on attention to its mechanical and electrical systems to keep it ready.
Calculating the true cost of a power shutdown
In both the Manchester and Birmingham incidents, the initial power loss was measured in seconds or, in CrossCountry’s case, hours. But the operational disruption lasted far longer. The Manchester outage displaced trains and crews across six operators and the effects ran into the following day. CrossCountry lost nearly an entire day of services and as a result is now conducting a review of its business continuity arrangements.
This is the pattern that critical infrastructure operators need to understand clearly. The direct outage is rarely the main event, as the real cost sits in the recovery. Even a very short interruption can displace complex, interdependent operations and trigger days of knock-on disruption where the commercial, operational and reputational damage far outweighs the seconds of power lost.
For organisations running control centres, communications hubs, data centres, hospitals or manufacturing facilities, the resilience of standby provision is often only proven the day it’s called on. By then, the specification, the maintenance, the testing and the transfer systems have either been done properly or they haven’t. There’s no middle ground.
The RMT has already called for a root and-branch review of railway control centres. Network Rail has commissioned an independent review of the Manchester incident, and CrossCountry has committed to examining its protection against external power outages. These are the right responses.
Any operation that depends on uninterrupted power, and whose backup arrangements haven’t been specified, tested and maintained to the standard the risk demands, is carrying a vulnerability that only needs one bad moment to expose.
The value of backup power is measured in the interruption it prevents, and August has been a sharp reminder of what happens when it doesn’t.