The £144m Scottish Government-funded electrification of the East Kilbride line reached operational status on Sunday 14 December, following completion of infrastructure works by Network Rail and its contractor partners.
The project commenced testing in October when a Class 380 electric train completed its first test run on the newly electrified route on 13 October, with engineers monitoring the overhead line equipment and train performance. This testing phase preceded the introduction of commercial electric services two months later.
Network Rail delivered the infrastructure programme working with contractor partners including SPL Powerlines, AmcoGiffen, Story, QTS, Rail Systems Alliance Scotland and Siemens. Works included installation of over 22km of overhead lines, double-tracking of 1.4km of railway between East Kilbride and Hairmyres, construction of new footbridges at Busby, Clarkston and Giffnock stations, track lowering under four bridges, and renewal of a railway bridge in Busby.
Two new stations were delivered as part of the enhancement programme: a £16m facility at Hairmyres which opened in May, and a £9m station building at East Kilbride which commenced operations in August. Additional infrastructure improvements included a new two-platform station with accessible footbridge at Hairmyres, replacement of the road bridge adjacent to Thornliebank station, a new footbridge at Busby, and improved accessibility features at Giffnock with a new accessible footbridge, plus a new footbridge at Clarkston with enhanced access to Platform 2.
ScotRail introduced a revised timetable on 14 December coinciding with the electric service launch. Four-carriage Class 380 electric units replaced Class 156 diesel trains on approximately 75 per cent of services between Glasgow Central and East Kilbride, with six-carriage Class 156 trains continuing to operate the remaining services. The timetable revision included additional evening services on the East Kilbride route, providing a broadly half-hourly frequency Monday to Saturday.
Gerry McQuade, capital delivery director at Network Rail Scotland, said the completion marked “the latest milestone in the story of Scotland’s Railway” and represented “a major transformation” in stations, facilities, accessibility and infrastructure. Joanne Maguire, ScotRail Managing Director, noted the introduction of Class 380 trains would deliver “smoother, quieter, and more sustainable journeys.”
The project received input from East Renfrewshire Council, South Lanarkshire Council, Glasgow City Council and Strathclyde Partnership for Transport to ensure integration with the wider transport network, including bus services and active travel links. SPT supported delivery of the new Hairmyres station and park-and-ride facility.